征服密实卵石层 高效施工展实力┃泰信卡特彼勒底盘钻机赋能乌兹别克斯坦最长桥梁建设

1  /  8
2025-06-23 17:16:37 中国路面机械网
上一张
  • 近日,在乌兹别克斯坦纳曼干桥桩项目施工现场,由江苏泰信机械股份有限公司(以下简称“泰信机械”)研发制造的卡特彼勒底盘 KR360C 旋挖钻机正高效运转,为这座当地备受瞩目的桥梁建设奠定坚实基础。该项目的顺利推进,不仅展现了中国桩工机械的卓越性能,更凸显了中国基建及桩工行业在全球市场的重要地位。
  • 	Recently, at the bridge pile project construction site in Namangan, Uzbekistan, the Caterpillar chassis KR360C rotary drilling rig developed and manufactured by TYSIM Piling Equipment Co., Ltd. (hereinafter referred to as "Tysim") is operating efficiently, laying a solid foundation for the construction of this highly anticipated bridge in the local area. The smooth progress of this project not only demonstrates the outstanding performance of Chinese pile driving machinery but also highlights the significant position of China's infrastructure and pile driving industry in the global market. Please provide the text you would like translated.
  • https://news-static.lmjx.net/upload/upfs/202506/23/990w743hf_1750670210385590.png!1024x1024.jpg
  • 复杂工程挑战重重
  • 	Complex engineering challenges
  • 	纳曼干大桥作为乌兹别克斯坦重点交通基础设施项目,主体预计 2025 年底竣工,建成后将成为该国最长桥梁。项目桩径 1.5 米,桩长 17 米,甲方对施工设备和工艺提出了极高要求。同时施工现场的地质条件复杂,0 ~8 米为卵石沙层,8 ~ 17 米则是密实卵石沙层,给项目施工带来了巨大挑战。
  • 	As a key transportation infrastructure project in Uzbekistan, the Namangan Bridge is expected to be completed in 2025 and will become the longest bridge in the country. The pile diameter of the project is 1500mm, and the piling depth is 17 meters, which places extremely high demands on construction equipment and technology. The geological conditions at the construction site are complex, with a pebble sand layer from 0 to 8 meters and a dense pebble sand layer from 8 to 17 meters, It brought huge challenges to the project construction.